| accepted risk: risk specified in a
contract for which the institution accepts liability;
acceptance: agreeing to a contractor's tender offer and
creating a binding contract;
accounting officer: the chief office bearer or appointed chief
executive ultimately responsible for the administration of the
institution. In a government department, this will be the Director
General or Head of Department, in local government, this will be the
Municipal Manager, and in other public entities, this will be the chief
executive officer (CEO) or similar;
activity description: a statement specifying what must be done
to achieve a desired result;
activity-on-arrow: a network diagram showing sequence of
activities, in which each activity is represented by an arrow, with a
circle representing a node or event at each end;
activity-on-node: a network where activities are represented
by a box or a node linked by dependencies;
activity schedule: document or pricing strategy that breaks
down the scope of work into a series of activities to allow contractors
to be paid a lump sum upon the completion of each of the activities;
actual cost: incurred costs that are charged to the project
budget and for which payment has been made, or accrued;
actual cost of work performed: total costs incurred (direct
and indirect) in accomplishing work during a given time period. ACWP is
used in the earned value method of progress measurement. See also earned
value analysis;
actual data: data that occurred after the start date of your
project plan;
actual finish date: the calendar date that work actually ended
on an activity. It must be prior to or equal to the data date. The
remaining duration of this activity is zero;
actual start date: the calendar date work actually began on an
activity. It must be prior to or equal to the data date;
advance payment: sum of money paid by an employer to the
contractor after the contract is signed, but before any work starts or
goods or services are supplied;
adjudication: a form of dispute resolution that unlike other
means of resolving disputes involving a third party intermediary, such
as conciliation or mediation, the outcome is a decision by a third party
which is binding on the parties in dispute. Normally the outcome would
be negotiated by the parties concerned, the third party is only a
referee in the process;
adjudicator: the third party intermediary appointed to resolve
a dispute between the parties in dispute by the process of
adjudication;
agent: a natural or juristic person who is not an employee of
the institution / employer who acts on the institution's / employer's
behalf;
approval: authorization give by the appropriate level of
authority of a stage reached within the delivery management cycle,
normally of a particular milestone, which provides authorization to
proceed with further activities and commitments;
approval levels: for clarity of responsibilities and
delegations, four levels of approval have been defined within the
delivery management system, which denote responsibility for approval at
the appropriate level within the authority and management hierarchy. The
levels defined are:
Level 1 - Controlling Authority - in terms of the PFMA the
Minister of a Department or Provincial MEC or Municipal Council or
Board of a SOE
Level 2 - Controlling Executive - the Accounting Officer of a
Department, Municipal Manager in a municipality or CEO in a SOE. This
can also comprise a high level committee within an organization
assigned specific authorities e.g. a procurement committee
Level 3 - Senior Management - management or a committee to whom
specific delegation of authority has been given
Level 4 - Project Management at a project level assigned to the
project manager as principle agent of a client within a construction
contract;
arbitration : a method of resolving disputes between two or
more parties by reference to one or more persons appointed for that
purpose, in accordance with procedures laid down in the Arbitration Act
42 of 1965;
arrow diagramming method: a network diagramming technique in
which activities are represented by arrows. The tail of the arrow
represents the start and the head represents the finish of the activity
(the length of the arrow does not represent the expected duration of the
activity). Activities are connected at points called nodes (usually
drawn as small circles) to illustrate the sequence in which the
activities are expected to be performed. See also precedence diagramming
method;
"as built "drawings: see record drawings;
back to top
baseline: minimum starting point of a project used for
comparing the performance of a project as delivery progresses;
best practice contractor recognition scheme: a best practice
recognition scheme referred to in section 21 of the Construction
Industry Development board Act (Act 38 0f 2000);
best practice project assessment scheme: a best practice
project assessment scheme referred to in section 23;
bid: see tender offer;
bidder: see tenderer;
bidding package: see procurement document;
bills of quantities: document or pricing strategy that lists
the items of work and the quantities and rates associated with each item
to allow contractors to be paid at regular intervals an amount equal to
the agreed rate for the work multiplied by the quantity of work
completed;
Board: the Construction Industry Development Board;
bond: sum of money or securities submitted to the employer or
placed in the hands of a third party to guarantee completion of the work
and recovery of the sums which the contractor would be recognised as
owing in terms of the contract;
budget at completion: the sum of all budgets allocated to a
project (BAC). It is synonymous with the term "Performance
Measurement Baseline;
budgetary allowance: see prime cost sum;
budgeted cost of work performed: the sum of the budgets for
completed portions of in-process work, plus the appropriate portion of
the budgets for level of effort and apportioned effort for the relevant
time period. BCWP is commonly referred to as Earned Value;
budgeted cost of work scheduled: the sum of the budgets for
work scheduled to be accomplished (including in-process work), plus the
appropriate portion of the budgets for Level of Effort and apportioned
effort for the relevant time period (BCWS);
back to top
category of works: construction works which may be categorised
as being one of the following:
- general building works;
- civil engineering works;
- electrical engineering works;
- mechanical engineering works; or
- specialist works;
centres of excellence: flagship state entity that is committed
to and is implementing good delivery management principles in line with
the Toolkit;
change control board: a formally constituted group of
stakeholders responsible for approving or rejecting changes to the
project baselines;
contractor grading: a designation in a categorization system
that indicates the capability that a contractor has to perform a
contract in a specified tender value range in a particular category of
works;
comparative offer: the tenderer's financial offer after the
factors of non-firm prices, all unconditional discounts and any other
tendered parameters that will affect the value of the financial offer
have been taken into consideration;
completion (practical completion): state of readiness for
occupation of the whole of the works although some minor work may be
outstanding;
completion certificate: document which certifies completion of
the works;
completion of defects certificate: document issued after the
end of the defects liability period that certifies that defects have
been made good;
conditions of contract: terms that collectively describe the
rights and obligations of contracting parties and the agreed procedures
for the administration of their contract;
conditions of tender: a document that establishes a tenderer's
obligations in submitting a tender and the employer's undertakings in
soliciting and evaluating tender offers;
construction industry: the broad conglomeration of
industries and sectors which add value in the creation and maintenance
of immovable assets within the built environment;
construction industry development: the broad process
/mechanism for ensuring that South Africa has sufficient capacity to
service its building and engineering infrastructure needs in pursuit of
a better life for all and an ability to export any surplus capacity it
may have from time to time;
Construction Industry Development Board (cibd):
- the board established in terms of section 2 of Construction
Industry Development board Act (Act 38 0f 2000);
- the Construction Industry Development Board including the Board
and the executive (i.e. officials employed by the cibd);
construction management: a project delivery system that uses a
construction manager to facilitate the design and construction of a
project by organizing and directing labour , materials, and equipment to
accomplish the purpose of the designer. A professional service that
applies effective management techniques to the planning, design, and
construction of a project from inception to completion for the purpose
of controlling time, cost and quality;
construction registers: the construction registers service
which the cibd provides to the clients and the industry including a
register of contractors and of projects;
contract: a legally enforceable agreement between an
institution/ employer and a contractor;
contract administration: managing the relationship with the
contractor;
contract data: document that states the applicable conditions
of contract and associated contract-specific data that collectively
describe the risks, liabilities and obligations of the contracting
parties and the procedures for the administration of the contract;
contract document: document represent all executed agreements
between the owner and contractor, any general, supplementary or other
contract conditions, the drawings and specifications, all bidding
documents less bidding information plus pre-award addenda issued prior
to execution of the contract and post-award change orders, and any other
items specifically stipulated as being included in the contract
documents, which collectively form the contract between the contractor
and the owner;
contract participation goal: a percentage of the value of the
contract which represents the inputs of targeted enterprises and/or
targeted labour in the performance of the contract;
contract strategy: the strategy which is adopted to procure
supplies, services, or engineering and construction works, to hire or
let moveable or immovable assets, to undertake disposals, or to operate
concessions in the most advantageous and cost effective manner;
contract sum: sum stated in the contract for the execution of
the work;
contractor: a natural or juristic person or partnership who
contracts with an institution to perform work;
contracting strategy: the strategy which is adopted to procure
supplies, services, or engineering and construction works, to hire or
let moveable or immovable assets, to undertake disposals, or to
operate concessions in the most advantageous and cost effective
manner;
contractor grading: a designation in a categorization system
that indicates the capability that a contractor has to perform a
contract in a specified tender value range in a particular category of
works;
contractual claim: claim the settlement of which is provided
for within the terms of the contract;
control account plan (previously called cost account plan): the
management control unit in which earned value performance measurement
takes place;
controlling authority: any institution having powers of
approval or sanction relating to a project or any component thereof;
corrupt practice: the offering, giving, receiving or
soliciting of anything of value to influence the action of the
employer or his staff or agents in the tender process;
cost: amount paid (or to be paid) by the employer for
supplies, services or works;
cost control: monitoring costs for comparison with the project
budget in order that control decisions can be taken;
cost performance index: the cost efficiency factor
representing the relationship between the actual costs expended and the
value of the physical work performed;
cost planning: cost control during the design process;.
cost plus contract: contract based on expended costs;
cost plus fixed fee: a form of contractual arrangement in
which the customer agrees to reimburse the contractor's actual costs,
regardless of amount, and in addition pay a negotiated fee independent
of the amount of the actual costs;
cost plus incentive fee: a type of contract where the buyer
reimburses the seller for the seller's allowable costs and the seller
earns a profit if defined criteria are met;
cost reimbursable: a pricing strategy in terms of which
the contractor is paid an agreed percentage fee to cover his
overheads and profit and is reimbursed at market related rates for
predefined cost items;
cost variance: the difference between the budgeted and actual
cost of work performed;
critical path method: a technique used to predict project
duration by analyzing which sequence of activities has the least amount
of scheduling flexibility. Early dates are figured by a forward pass
using a specific start date and late dates are figured by using a
backward pass starting from a completion date;
back to top
data date: the calendar date that separates actual
(historical) data from scheduled data;
day work: work carried out as part of a contract and paid for
on the basis of actual cost to the contractor of labour, materials and
plant, plus an agreed percentage to cover overhead charges and profits;
defect: nonconformity of an item to a specified requirement;
defects liability period: period from completion during which
the contractor has an obligation to make good defects in the materials
and workmanship covered by the contract that are indicated by the
employer or his representative;
deliverable:
- any measurable, tangible, verifiable outcome, result or item that
must be produced or completed;
- specific output that is expected to result within each strategic
objective i.e. measurable objective;
delivery management:
- the management of the administration of the process of
infrastructure and public service delivery;
- the management of the process of public service delivery as
applied to infrastructure and maintenance projects;
demand management: involves creative intervention in the
market to influence demand for services and infrastructure with
forecasted consequences;
design and build: a contracting strategy whereby the
contractor undertakes most of the design and all construction in
accordance with the employer's brief and his detailed tender submission,
usually for a lump sum price;
design by employer: a contracting strategy in terms of which
the contractor undertakes only construction on the basis of full designs
issued by the employer;
develop and construct: a contracting strategy similar to
design and build, except that the employer issues a concept design on
which tenders are based;
direct financial premium: the difference between the financial
offer of the lowest acceptable financial offer received and the offer
which receives the highest number of tender evaluation points in terms
of the goal/price mechanism and which is awarded the contract by the
contracting authority;
disposal: the divestiture of assets, including
intellectual property and other rights and goodwill by any means,
including sale, rental, lease, license, tenancy, franchise, auction or
any combination thereof;
domestic subcontractor: subcontractor appointed by the main
contractor at his discretion;
drawing: information presented in a graphical manner that may
include annotations;
duration: the length of time needed to complete an activity;
back to top
early finish date: in the critical path method, the earliest
possible date on which the uncompleted portions of an activity (or the
project) can finish based on the network logic and any schedule
constraints. Early finish dates can change as the project progresses and
changes are made to the project plan;
early start date: in the critical path method, the earliest
possible date on which the uncompleted portions of an activity (or the
project) can start based on the network logic and any schedule
constraints. Early start dates can change as the project progresses and
changes are made to the project plan;
earned value: a measure of the value of work performed so far.
Earned value uses original estimates and progress-to-date to show
whether the actual costs incurred are on budget and whether the tasks
are ahead or behind the baseline plan;
earned value analysis: a measure of the project's progress,
forecasting its completion date and final cost. A provision of schedule
and budget variances along the progress of a project;
earned value management: a management technique that relates
resource planning to schedules and to technical cost and schedule
requirements. All work is planned, budgeted, and scheduled in
time-phased increments constituting a cost and schedule measurement
baseline;
emerging enterprise: an enterprise which is owned, managed and
controlled by black persons and which is overcoming business impediments
arising from the legacy of apartheid;
emerging sector: that sector of the construction
industry which comprises emerging enterprises;
employer: natural or juristic person or partnership entering
into the contract with the contractor for the provision of supplies,
services, or engineering and construction works;
employment-intensive: a generic expression that is used to
describe strategies, programmes, projects, activities and assets which
will promote direct, short-term or long-term employment generation at
the highest possible level;
engineering and construction works: the provision of a
combination of supplies and services, arranged for the development,
extension, installation, repair, maintenance, renewal, removal,
renovation, alteration, dismantling or demolition of structures,
including building and engineering infrastructure;
estimate at completion: actual cost of work completed to date
plus the predicted costs and schedule for finishing the remaining work;
estimate to complete: the value expressed in either dollars or
hours developed to represent the cost of the work required to complete a
task. The ETC is calculated as BAC - BCWP;
Executive Authority:
- in relation to a constitutional institution consisting of a body
of persons (e.g. a board of directors), means the chairperson on the
constitutional organization.
- in relation to a constitutional institution with a single office
bearer (e.g. a government department or municipality), means the
incumbent of that office (e.g. the Minister, MEC or Executive
Mayor);
expenditure per unit of employment generated: the ratio of the
total construction cost, including any management fees directly related
to construction activities, to the total employment opportunities that
are generated in the construction and maintenance of infrastructure;
expression of interest: documentation used to register a
respondent's interest in undertaking a specific contract or to
participate in a project or programme and to obtain their credentials so
they may, in terms of the institution's procurement procedures, be
invited to submit a tender offer should they qualify to do so;
extension of time: allowance of extra time for a delay
occasioned by causes outside of a contractor's control and not included
in his risks;
back to top
feasibility report: document reporting on the technical,
social, environmental and economic implications of a proposed project;
final sum: total sum in the final account;
finish-to-start: a dependency between two project activities
or between a project activity and a milestone;
firm price contract: contract in which the price cannot be
amended despite changes in economic conditions;
Note: The final sum in a firm price contract may
vary from the tendered sum or contract amount due to changes in the
quantum of work executed or supplies delivered. It may not,
however, be varied due to currency fluctuations , the rise or fall of
material and fuel prices, consumer inflation etc.
final account: a document that states the cost of the total
work carried out and the total payment to be made in terms of the
contract, as accepted by the parties;
fixed price contract: contract in which the contract sum is
given in the tender or is based on bills of quantities;
fixed-price-incentive-fee: provides the supplier with a fixed
price for delivered performance plus a predetermined fee for superior
performance;
force majeure: event that is unforeseeable, insurmountable and
outside the influence of the parties to a contract and prevents a
contractor fulfilling his obligations either in part or in full;
forms of offer and acceptance: documents that formalize the
legal process of offer and acceptance;
forms of securities: documents that provide for the securities
required by the employer;
forms for adjudicator appointments: documents that establish
the terms and conditions upon which the adjudicator is to be
appointed;
fraudulent practice: a misrepresentation of the facts in order
to influence the tender process or the execution of a
contract arising from a tender offer to the detriment of the employer,
including collusive practices intended to establish prices at an
artificial level;
free float or finish-to-finish: the maximum amount by which an
activity can be delayed beyond its early dates without delaying any
successor activity beyond its early dates;
function: a designated duty or particular activity or
operation performed in response to a process, procedure or aspect
thereof;
back to top
goal/price mechanism: system of tender
evaluation which measures value for money in terms of the financial
offer and goals emanating from a preferential procurement policy by
awarding tender evaluation points for price and for under-takings to
attain contract participation goals in the performance of a contract for
the status of an enterprise in terms of specific parameters;
good practice agents: built environment professionals from the
private sector contracted to assist departments in the roll out of the
toolkit;
graphical evaluation and review technique: a network analysis
technique that allows for conditional and probabilistic treatment of
logical relationships (i.e., some activities may not be performed);
back to top
handover: process of handing over the work at the site to the
client upon completion, without reservation;
back to top
IDP: Integrated Development Plan as implied in the Municipal
Systems Act and Municipal Structures Act;
implementing agent: an agent appointed by a sponsoring
department/SOE to implement a infrastructure/maintenance programme on
behalf of the sponsor. The implementing agent may be another department
(for example public works implementing on behalf of Health who is the
sponsoring department) or another agent for example the Independent
Development Trust;
infrastructure: in the context of the Toolkit means any
building, construction or engineering works constructed for the
betterment of the built environment and includes maintenance works;
infrastructure programme: in the context of this toolkit means
a programme or portfolio of infrastructure and/or maintenance projects
which are implemented by departments/SOE in terms of their
infrastructure and maintenance objectives;
Note: The term is not used to describe the
departmental programmes (i.e. business units and associated budgets)
as defined within the strategic plans of departments;
infrastructure programme implementation plan (IPIP): (also
referred to as an infrastructure programme business plan) which sets
down how the infrastructure/maintenance programme will be formulated,
planned, managed and implemented. It includes the following elements:
objectives, targets, institutional framework, contracting arrangements,
programme management structure, budgets and cash flows , timeframes,
communications, monitoring and reporting, risk and quality management;
institution: a public body i.e. a department, trading
entity, constitutional institution, municipality, public entity or
municipal entity;
interim certificate: document that authorises payments to be
made for work executed or materials supplied up to a given date;
interim payment: payment as per the interim certificate that
results from an interim valuation;
interim valuation: interim statement agreed between the
parties of the total value of work carried out at a certain date and
sums to be paid;
instructions: requirements by the employer or his
representative, made or confirmed in writing to the contractor,
regarding the carrying out of the contract;
invitation for bid: similar to a request for proposal, but
often with a more specific application area;
IPIP: see infrastructure programme implementation plan;
back to top
joint venture: means a grouping together two or more
contractors who jointly and severally undertake to perform an
engineering and construction works contract;
back to top
KPI : key performance indicator used to measure performance
and achievement of an objective or result, also referred to as OVI
standing for objectively verifiable indicators by some funders;
back to top
labour: all persons involved in physical
construction work;
labour-based: in relation to the production process and
technologies used in the production of goods and materials and in
construction works, means methods of production and technologies that
are designed and managed so as to promote the creation of employment
with predetermined socio-economic benefits;
labour-only contract: contract for the supply of labour;
late finish date: in the critical path method, the latest
possible date that an activity may be completed without delaying a
specified milestone (usually the project finish date);
late start date: in the critical path method, the latest
possible date that an activity may be begun without delaying a specified
milestone (usually the project finish date);
level of effort: an activity that does not readily lend itself
to measurement of discreet accomplishment. It is generally characterized
by a uniform rate of activity over a specific period of time;
life cycle costing: the concept of including acquisition,
operating and disposal costs when evaluating various alternatives;
liquidated damages: sum deducted under the contract from the
total of payments due in the event of any delay with regard to
contractual obligation;
list of returnable documents: document that lists everything
the employer requires a tenderer to submit with his tender submission;
litigation: the system by which the advocates representing
each side adduce arguments in a court of law to persuade the tribunal
(judge, jury or assessors) that they have the better legal case;
lump sum contract: fixed price contract based on a single
tendered amount;
back to top
main contractor: a contractor acting as an employer by
subcontracting part of his contract;
maintenance: in the context of the Toolkit means the
refurbishment and repair of infrastructure;
maintenance manual: document that contains advice on the care
and servicing requirements of engineering and construction works;
management contract: a contracting strategy in terms of which
a management contractor is appointed to engage and manage a number of
trade contractors to carry out construction on the basis of designs
issued by the employer, as and when they are completed;
Note: The trade contracts in a management
contract are between the management contractor and the various trade
contractors.
measurable objectives: (or deliverables) identify very
specific things that an organization intends to do or deliver in order
to achieve its strategic objectives and ultimately its strategic goals.
For the purpose of the strategic planning process described in this
toolkit, measurable objectives need to comply with the SMART principle,
i.e. objectives need to be specific, measurable, achievable, relevant
and time-bound.
measured work: details of the quantities and descriptions of
the works to be carried out or already carried out;
MEC: Member of the Executive Council;
mediation: a form of dispute resolution involving a third
party intermediary which is intended to produce an agreement or
conciliation between the parties to a contract;
method of verification: method for confirming, substantiating and
ensuring that an activity or condition has been implemented in
conformity with specified requirements;
Medium Term Expenditure Estimates (MTEE): expenditure
estimates contained in the Medium Term Expenditure Framework;
Medium Term Expenditure Framework (MTEF): a document which
details 3-year rolling expenditure and revenue plans for national and
provincial tiers of government;
MTEF: Medium Term Expenditure Framework;
MFMB: Municipal Finance Management Bill which will eventually
guide financial management for local government;
milestone: a significant event in the delivery management
cycle, usually the completion of a major or critical deliverable;
monitoring: the capture, analysis and reporting of
performance, usually compared to plan or targets;
back to top
nominated subcontractor: a subcontractor nominated by the
employer which the contractor is obliged to appoint as a subcontractor;
nominal: money term that includes inflation - "What you
see is what you get";
non-firm price contract: contract in which the prices are
amended to reflect changes in economic conditions;
back to top
official: an employee of the institution who acts on the
institution's behalf;
operational manual: document that contains instruction and
advice on the use of equipment;
organ of state: see institution;
organization(al) breakdown structure: a hierarchical structure
designed to pinpoint the area of an organization responsible for each
part of a project (OBS);
OVI: see KPI;
back to top
partnering: the extension of the practice of common sense team
working into a formal structure agreed to by the parties;
partnering departments: willing and committed partners i.e.
departments who wish to enhance their capacity with respect to
management of infrastructure delivery and implement the toolkit to bring
about such improvements;
party: either of the organisations that have entered
into a contract for the provision of supplies, services or engineering
and construction works;
percent complete: an assessment of how far along a task has
progressed as a percentage of its total duration. As the assessment is
very often subjective, it should not be relied upon as a firm basis for
quantitative analysis of a project's progress. A better approach is the
use of Earned Value Analysis;
performance measurement baseline: a project's realistic
executable contract plan (PMB);
performance monitoring: continuous or periodic quantitative
assessment of the actual performance compared with specific objectives,
targets or standards;
permanent works: permanent work to be executed under the
contract;
permissible deviation: the specified limit(s) of deviation
within which a size or position must lie;
PFMA: Public Finance Management Act, no 1 of 1999 which guides
financial management for national and provincial government departments
and other listed public entities, including SOEs;
phase: section of work that arises from splitting up of a
project or a contract in accordance with a definite agreement or a
collection of logically related activities, usually culminating in a
major project deliverable;
plan of work: document that details principal stages within
project delivery and which identifies main tasks and persons;
planned finish date: see scheduled finish date;
planned start date: see scheduled start date;
planned value: the sum of the budgets for all planned (earned
value) work, scheduled to be accomplished within a given time period.
Also known as the Budgeted Costs for Work Scheduled (BCWS);
PMU:Programme management unit responsible for managing the
implementation of the infrastructure programme;
practical completion certificate: a certificate issued by the
employer or duly authorized representative of the employer in terms of
the contract that signifies that the whole of the works have reached a
state of readiness for occupation or use for the purposes intended
although some minor work maybe outstanding;
pre-contract stage: stage of work covering events up to the
point when a contract is placed;
precedence diagramming method: a network diagramming technique
in which activities are represented by boxes (or nodes). Activities are
linked by precedence relationships to show the sequence in which the
activities are to be performed;
preferential procurement policy: the policy(s) developed by an
institution in accordance with the requirements of section 217(2) of the
Constitution of the Republic of South Africa (Act 108 of 1996) and the
Preferential Procurement Policy Framework Act (Act 5 of 2000);
Note: a preferential procurement policy promotes
objectives additional to those associated with the immediate objective
of the procurement itself.
price: the financial offer;
price adjustment: specific method of calculating the amount to
be added or to be deducted from the contract sum by way of allowances
for increases or decreases in the costs of labour, plant and materials
occurring during the currency of the contract using a price variation
formula;
priced bill of quantities: bill of quantities that contains
the contractor's rates extended and totalled to give the tendered sum;
price variation formula: formula for amending contract prices
to reflect changes in economic conditions;
pricing instructions: document that provides the criteria and
assumptions which it will be assumed in the contract that have been
taken into account when developing prices, or target in the case of
target cost contracts;
pricing strategy: the strategy which is adopted to
secure prices and to remunerate contractors in terms of the contract;
prime contract: see main contractor;
prime cost sum: amount included in a contract for work that is
foreseen but cannot be accurately specified at the time the tender
documents are issued;
principal: a person who is a partner in a partnership, a
sole proprietor, a director in a company established in terms of
the Companies Act, or a member of a close corporation registered in
terms of the Close Corporation Act;
process: a succession of logically related actions occurring
or performed in a definite manner which culminates in the completion of
a major deliverable or the attainment of a milestone;
procurement: the process which creates, manages and fulfils
contracts relating to the provision of supplies, services or engineering
and construction works, the hiring of anything, disposals and the
acquisition or granting of any rights and concessions;
Note: Procurement as such is concerned with
activities that both precede and follow the signing of a contract.
procurement document: documentation used to solicit and
evaluate an expression of interest for or to initiate and conclude a
contract;
procurement procedure: the selected procedure for the
solicitation of tender offers in a specific procurement;
procurement strategy: the contracting, pricing and targeting
strategy and procurement procedure that is selected for a contract;
programme: see "infrastructure programme" for the
distinction used to define a programme or portfolio of infrastructure
projects whereas a "departmental programme" as referred to in
the strategic plan is a "strategic programme" within a
department against which specific budget is allocated in order to
achieve specific strategic outcomes. A group of related projects managed
in a coordinated way. Programmes usually include an element of ongoing
work;
programme implementing agent: an agent appointed by a sponsoring
department/SOE to implement a infrastructure/maintenance programme on
behalf of the sponsor. The programme implementing agent may be another department
(for example public works implementing on behalf of Health who is the
sponsoring department) or another agent for example the Independent
Development Trust;
programme management: management of the
infrastructure/maintenance programme to implement a number of projects
utilising a common delivery management process;
project: a temporary endeavour undertaken to create a unique
product, service or result;
project delivery: undertakings planned by an institution which
impact directly on the services that they are mandated to deliver;
project life cycle: a collection of generally sequential
project phases whose name and number are determined by the control needs
of an organization/s involved in the project;
project management: the application of knowledge, skills,
tools and techniques to plan activities to meet the project
requirements. Also defined as the art and science of managing a project
from inception to closure as evidenced by successful product delivery
and transfer;
project management body of knowledge (PMBOK®): an inclusive
term that describes the sum of knowledge within the profession of
project management;
Project Management Professional ®: an individual certified as
such by the Project Management Institute.
PMI® requires users of the PMP® symbol to do the
following: "Include the registered trademark symbol,
"®", immediately next to each use or appearance of the
"PMP" ® mark, as well as acknowledge and state in a
prominent portion of the publication on which the mark appears, that
"PMP" ® is a registered service mark of the Project
Management Institute, Inc."
provisioning: the acquisition, storage and issuing of
consumables or supplies or ect isthe acquisition of services required to
meet the day to day operating requirements of an institution;
public private partnership: a commercial transaction between
an institution and a private party in terms of which:
- the private party either performs an institutional function on
behalf of the institution for a specified or indefinite period; or
acquires the use of state property for its own commercial purposes
for a specified or indefinite period; and
- the private party receives a benefit for performing the function
or by utilising state
property, either by way of:
i) compensation from a revenue fund;
ii) charges or fees collected by the private party from users or
customers of a service provided to them; or
iii) a combination of such compensation and such charges or
fees;
back to top
QMP: quality management plan formulated in order to monitor
the quality of the results of the programme, particularly how quality
will be ensured within each project i.e. what quality checks will be
carried out when and by whom etc;
quality assurance: the function of Quality Assurance is the
responsibility of (reports to) the Project Manager and is responsible
for ensuring that project standards are correctly and verifiably
followed by all project staff;
quality control: the process of monitoring specific project
results to determine if they comply with relevant standards and
identifying ways to eliminate causes of unsatisfactory performance;
back to top
record drawings: drawing that records the final state of the
engineering and construction works as constructed or built;
remaining duration: the estimate of time remaining to complete
an activity. A far more useful measure of progress than percentage
complete;
request for proposal: a formal invitation containing a scope
of work which seeks a formal response (proposal) describing both
methodology and compensation to form the basis of a contract;
request for quotation: a formal invitation to submit a price
for goods and/or services as specified. Equivalent to a request for
proposal but with more specific application areas;
resource specification: performance specification which
establishes requirements for the engagement of targeted enterprises,
targeted labour or a combination thereof in the performance of a
contract and indicates the means by which such engagement can be
measured, quantified and verified;
resident engineer: engineer employed on site to supervise work
during construction;
responsibility assignment matrix: the RAM correlates the work
required by a Contract Work Breakdown Structure (CWBS) element to the
functional organization responsible for accomplishing the assigned
tasks. The responsibility assignment matrix is created by intersecting
the CWBS with the project Organizational Breakdown Structure (OBS). This
intersection identifies the cost account;
respondent: a natural or juristic person or partnership who
submits an expression of interest in response to an invitation to do so;
retention sum: sum retained for a certain period by the
employer to offset costs which may arise from the contractor's liability
for defects or failure to comply fully with the contract;
returnable schedule: document that a tenderer is required to
complete for the purpose of evaluating tender offers or a document which
upon acceptance of a tender offer forms part of the subsequent contract;
risk: combination of the probability of occurrence of harm and
the probable severity of that harm;
risk assessment: the assessment performed when evaluating
tender offers to determine the level of commercial risks posed thereby;
risk management: the application of a formal process to the
range of possible values to key factors associated with a risk in order
to determine the resultant range of outcomes and their probability of
occurrence;
back to top
schedule: documentation in the form of tables
or detailed lists;
schedule of rates: schedule in which the prices applicable to
the various items of work are listed;
scheduled finish date or start-to-finish: the date work was
scheduled to finish on an activity. The scheduled finish date is
normally within the range of dates delimited by the early finish date
and the late finish date;
schedule performance index: the ratio of BCWP to BCWS i.e. SPI
= BCWP / BCWS. A positive value (i.e. greater than 1) indicates that
work is ahead of schedule. A negative value (i.e. less than 1) indicates
that work is behind schedule;
scheduled start date or start-to-start: the date work was
scheduled to start on an activity. The scheduled start date is normally
within the range of dates delimited by the early start date and the late
start date;
schedule variance: any difference between the projected
duration for an activity and the actual duration of the activity. Also
the difference between projected start and finish dates and actual or
revised start and finish dates;
scope of work: the specification and description of the
supplies, services, or engineering and construction works which are to
be provided and any other requirements and constraints relating to
the manner in which the contract work is to be performed;
security: see bond;
selected subcontractor: a subcontractor selected by the
contractor in consultation with the employer in terms of the
requirements of the contract;
services: the provision of labour or work, including
knowledge-based expertise, carried out by hand, or with the assistance
of equipment and plant;
site: the land and any other places made available by the
employer for the purposes of the contract, on, under, over, in or
through which the works are to be executed or carried out;
site information: document that describes the site as at the
time of tender to enable the tenderer to price his tender and to decide
upon his method of working and programming;
SOE:
- state owned enterprise (Parastatals);
- state owned enterprises, in the context of the Toolkit are
organisations responsible for funding and providing certain
infrastructure and maintenance of infrastructure within South Africa
(for example ESKOM, TRANSNET, TELKOM etc);
sponsor:department, municipality or state owned enterprise
that is responsible for the infrastructure programme and for funding it;
sponsoring department/SOE: the department or SOE
responsible for funding and providing infrastructure or maintenance;
statement of work: a narrative description of the work to be
performed;
strategic goals: (also referred to as outcomes)
- are the desired outcomes resulting from the strategic intervention
and are the areas of organisational performance that are critical to
the achievement of the public institution's mission;
- strategic goals also describe the strategic direction of the
organization and should focus on service delivery,
management/organization, financial management, training and
learning.
- Strategic goals normally span at least five years, but are likely
to be applicable to a longer period.
strategic objectives: strategic objectives (also referred to
as outputs) are the specific outputs to achieve the goal (or the
outcome). Strategic objectives are more concrete and specific than
strategic goals, but should link directly to the strategic goals;
These would span at least three years, but are likely to be
applicable to a longer period.
strategic plan: strategic objectives (also referred to as
outputs) are the specific outputs to achieve the goal (or the
outcome). Strategic objectives are more concrete and specific than
strategic goals, but should link directly to the strategic goals;
subcontracting: a plan containing the long-term goals and
strategies of an organization;
subcontractor: contractor to whom a main contractor has
contracted part of his work;
submission data: document that establishes the respondent's
obligations in submitting an expression of interest and the employer's
undertakings in the processing of the submission;
supplies: the provision of materials or commodities made
available for purchase;
supply chain management: the management of the supply chain
processes and activities;
sustainable construction: the broad process/ mechanism for the
realisation of human settlements and the creation of infrastructure that
supports sustainable development, including:
- the extraction and beneficiation of raw materials,
- the manufacturing of construction materials and their components,
- the construction project cycle from feasibility to design and
deconstruction, and
- the management and operation of the built environment;
sustainable development: development that meets the needs of
the present without compromising the ability of future generations to
meet their own needs;
Note: Sustainable development is a far more
embracing and holistic concept than environmental sustainability. It
is a way of looking at all the sources and resources that can lead to
a higher quality of life for the current generation, without
compromising future generations.
back to top
target completion date: an imposed date which constrains or
otherwise modifies the network analysis;
target cost: a pricing strategy in terms of which the
contractor is paid for work done on a cost reimbursable basis. The
difference between the final cost of the works and a target price agreed
at initial conclusion of the contract is shared between the contractor
and the employer in accordance with a pre agreed formula;
target start date: an imposed starting date on an activity.
Most PM software will not schedule an early start date earlier than the
target start date;
targeted enterprise: an enterprise which is preferred in terms
of an institution's preferential procurement policy and which complies
with defined enterprise characteristics;
targeted labour: project specific or permanent employees of a
contractor that are preferred in terms of an institution's preferential
procurement policy;
targeted procurement procedure: the process used to
create a demand for the services and supplies from, or to secure the
participation of, targeted enterprises and targeted labour in
contracts in response to a targeted procurement system to achieve the
objectives of the targeting strategy;
targeted procurement : a system of procurement which is used
to create a demand for the services and supplies from, or to secure the
participation of, targeted enterprises and targeted labour in
contracts in response to the targeting strategy to achieve the
objectives of a preferential procurement policy;
targeting strategy: the approach which is adopted in
procurement to implement a preferential procurement policy;
technical specification: written criteria that augment the
drawings pertaining to the technical construction of the project that
cannot be conveniently included on the plans;
temporary works: all temporary works of every kind required
(other than equipment , i.e. apparatus, machinery, vehicles, etc)
required on site for the execution of and completion of the permanent
works and the remedying of defects;
tender: see tender offer;
tender data: document that establishes the tenderer's
obligations in submitting a tender and the employer's undertakings in
administering the tender process and evaluating tender offers;
tender notice and invitation to tender: document that alerts
prospective contractors to the nature of the supplies, services and
engineering and construction works required by the employer and contains
sufficient information to solicit a response;
Tender Value Range (TVR): a minimum and maximum tender
price, including Value Added Tax, used to categorise the capability of
tenderers to execute an engineering and construction works
contract falling within these two limits;
tender offer: a formal offer to execute a contract for
monetary reward under prescribed conditions which is capable of
acceptance and conversion into a binding contract;
tender submission: a submission made by a tenderer in response
to an invitation to tender/ procurement document;
tenderer: a natural or juristic person or partnership who
submits a tender offer to execute a contract in response to an
invitation to do so;
term contract: contract that enables the employer to order
work during a prescribed period at agreed rates;
termination: bringing a contract to an end before its
completion under conditions specified in the contract or at common law;
tolerance: the range between the limits within which a size or
position must lie;
Toolkit: Toolkit (Infrastructure Delivery Management System)
for management of infrastructure delivery comprising a delivery
management system and associated guidelines;
total float or target finish date: the date planned to finish
work on an activity;
total quality management (TQM): an organizational approach to
customer satisfaction involving customers, people and the continuous
improvement of processes;
unit rate: price applied per unit of works, goods or services;
unforeseeable: not reasonably foreseeable by an experienced
contractor by the date for submission of tenders;
back to top
value engineering: an organized effort to analyze the
functions of systems, equipment, facilities, services, and supplies for
the purpose of achieving the essential functions at the lowest life
cycle cost consistent with required performance, reliability, quality,
and safety;
value management: an evaluation process which addresses the
technical and functional dimensions at the early stages of a project to
ensure a fully integrated approach has been taken, the project is
consistent with strategic goals and non-build solutions have been
properly assessed;
variation of price contract: see non-firm price contract;
variation: alteration to the nature or extent of construction
works, or the conditions under which they will be carried out;
variation order: instruction that makes a variation;
verification: confirmation by examination of evidence that
specified requirements have been met;
back to top
work breakdown structure: a task oriented detailed breakdown,
which defines the work packages and tasks at a level above that defined
in the networks and schedules. The WBS initiates the development of the
Organizational Breakdown Structure (OBS), and the Cost Breakdown
Structure (CBS). It also provides the foundation for determining Earned
Value and activity networks;
work item: see activity;
works: see engineering and construction works;
back to top
|